Perbaikan Turap Waduk Bojong Indah Capai 70 Persen

Bojong Indah Reservoir Plastering Reaches 70 Percent

The improvement of Bojong Indah Reservoir plaster on Jalan Belimbing Raya, RT 05/11, Rawa Buaya Urban Village, Cengkareng Sub-district, West Jakarta, is being rushed.

We are targeting two months

West Jakarta Water Resource Sub-agency Head, Purwanti, said repairs were carried out after the retaining wall collapsed then causing damage. Repairs began in mid-February 2024, spanning 48 meters.

"Now the repair has reached 70 percent," Purwanti said, Thursday (9/5).

E. Jakarta Mayor: Pekayon Emaung Must Have Drainage Tank

Purwanti added that the project involves 15 personnel of West Jakarta Water Resource Sub-agency with one excavator.

"Currently, personnel are digging the ground and installing dolken wood. Next, river stones will be installed and plastered using a mixture of sand and cement. We are targeting two months for this repair to be completed," Purwanti stated.

Linked News
Popular News indeks
  1. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye1373 personFakhrizal Fakhri
  2. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye1034 personAldi Geri Lumban Tobing
  3. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye960 personAldi Geri Lumban Tobing
  4. CNY 2577 Kongzili: Matakin Calls for Justice and Solidarity

    access_time22-02-2026 remove_red_eye835 personAldi Geri Lumban Tobing
  5. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye734 personAldi Geri Lumban Tobing